To the news list

In section B-6 of the third stage, the arrangement of the vertical of the sixth floor is underway

July 19, 2023

RIEL Real Estate Corporation reports that the construction of Mistechko Pidzamche RC is actively pursued. In section B-6 of the third stage of Brama complex, the installation of vertical monolithic structures of the sixth floor is being carried out, and the laying of the outer walls is in progress.

In section B-5, monolithic work has been completed, and the exterior walls are being laid. In section B-1, walls are being laid, in section B-2, a floor slab of the fifth floor has been equipped.

In the second stage, in sections B-1, B-2, B-3, gravel filling of the flat roof continues, in section B-3, the installation of the sloping roof is being completed. The work on the improvement of the adjacent territory is underway.

In the first stage, the installation of electricity metres and the arrangement of railings in the common facilities in all sections are being completed.

You can choose the floor and layout, as well as find out other details on the conditions for purchasing an apartment in Mіstechko Pidzamche RC, in our sales department. Contacts at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ЧП «Львівінтерсервіс»

ООО «Вежа на Хмельницького»

ООО «Брама на Хмельницького»

Join our social networks
Contact us in convenient way
(032) 229-54-63
Feedback
The exchange rate as of 5/17/2024 is 39.69 UAH.
Sales departments
Lviv, 10, Volodymyra Velykoho Street
© 2024  Pidzamche. Brama. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.