In the first stage, the installation of water metres in all sections has been completed

August 31, 2023

Real Estate Corporation RIEL reports that Mistechko Pidzamche residential complex construction is actively pursued. In the fifth stage of Brama complex the installation of water meters in all sections has been completed, the smoke exhaust systems in the parking lot are fully ready; preparations for the installation of elevators are underway.

In the second stage, in B-1 and B-2 sections, the arrangement of the roof is in progress; in B-3 section, the builders have completed the sloping roof installation; work on the improvement of the local area continues.

In the third stage, in V-1 section, the laying of external walls is being performed; in V-2, the vertical of the sixth floor has been completed; in V-5 and V-6 sections, monolithic work has been completed, the laying of external walls is in progress, and ventilation systems are being installed.

You can choose the floor and layout and find out other details about the sales terms for purchasing an apartment in Mіstechko Pidzamche RC in our sales department. Contacts are at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ЧП «Львівінтерсервіс»

ООО «Вежа на Хмельницького»

ООО «Брама на Хмельницького»

Join our social networks
Contact us in convenient way
(032) 229-54-63
Feedback
The exchange rate as of 5/17/2024 is 39.69 UAH.
Sales departments
Lviv, 10, Volodymyra Velykoho Street
© 2024  Pidzamche. Brama. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.