Mistechko Pidzamche RC: in sections A-1, A-2 of the first stage of Brama complex, the arrangement of internal water supply and sewerage systems is under way

June 14, 2021

RIEL Real Estate Corporation reports that construction work of Mistechko Pidzamche residential complex is actively pursued. Now in sections А-1, А-2 of the first stage of the Brama complex, the arrangement of internal water supply and sewerage systems is under way. This was announced by the head of the construction project.

In section А-5 the floor slab casting is completed on the 4th floor.

It is also reported that in section A-6, the installation of vertical structures of the attic floor has been completed, and in section A-7, the walls blockwork is in progress.

Meanwhile, the workers are completing the arrangement of the walls waterproofing.

To choose the floor and layout, to learn more on the terms of purchasing an apartment in Mistechko Pidzamche RC – in the sales departments of the company at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ЧП «Львівінтерсервіс»

ООО «Вежа на Хмельницького»

ООО «Брама на Хмельницького»

Join our social networks
Contact us in convenient way
(032) 229-54-63
Feedback
The exchange rate as of 11/26/2024 is 41.43 UAH.
Sales departments
Lviv, 116, Bohdana Khmelnytskoho Street
© 2024  Pidzamche. Brama. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.