In the third stage of the Brama complex in V-4 section, the arrangement of the third floor columns continues

September 23, 2024

RIEL Real Estate Corporation continues to actively work on the construction of the Mistechko Pidzamche Residential Complex. In the third stage of the Brama complex, in V-4 section, the arrangement of columns on the third floor is underway.

In addition, the installation of steel structures for the sloping roof is nearing completion in section V-2, and work is underway on the construction of the pit in V-3 section. In V-5 and V-6 sections, ventilation ducts, sewer risers and chimneys are being lined. In section V-6, façade works are actively underway.

In the second stage, in B-1 and B-2 sections, the masonry of the attic floor walls has been completed, preparations for the installation of steel roof have been made, and the backfill of the passage between the sections has been completed.

The first stage of the complex has already been successfully commissioned, which creates additional benefits for investors.

We invite you to choose your ideal apartment in the Mistechko Pidzamche RC. For more information and advice, please contact our sales team at the contacts listed on our website.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ЧП «Львівінтерсервіс»

ООО «Вежа на Хмельницького»

ООО «Брама на Хмельницького»

Join our social networks
Contact us in convenient way
(032) 229-54-63
Feedback
The exchange rate as of 11/21/2024 is 41.35 UAH.
Sales departments
Lviv, 116, Bohdana Khmelnytskoho Street
© 2024  Pidzamche. Brama. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.