In the third stage of Brama complex, installation of chimney pipes is underway

October 24, 2023

Real Estate Corporation RIEL reports that the construction of Mistechko Pidzamche residential complex is actively pursued. In the third stage of Brama complex, installation of chimney pipes is underway. In sections B-2, B-5, B-6 monolithic work has been completed; at the same time in sections B-5, B-6 the sanitary sewer system and rain drain are being installed.

In the second stage, the foundation slab of the passage between sections B-1 and B-2 is being reinforced and neighbourhood improvement is almost over.

In the first stage, the installation of elevators in sections A-1 and A-2 has been completed. Work is in progress in sections A-3 and A-5.

You can choose the floor and layout and find out other details about purchase conditions of apartments in Mistechko Pidzamche RC in our sales department. Contacts are at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ЧП «Львівінтерсервіс»

ООО «Вежа на Хмельницького»

ООО «Брама на Хмельницького»

Join our social networks
Contact us in convenient way
(032) 229-54-63
Feedback
The exchange rate as of 5/17/2024 is 39.69 UAH.
Sales departments
Lviv, 10, Volodymyra Velykoho Street
© 2024  Pidzamche. Brama. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.